Wednesday, 21 May 2014

Introduction

The development for Guinness Hermitage began approximately 8 weeks ago, with the clearing of the site and establishment of the site facilities and compound.

Since then we have installed 90% of the underground drainage, all of the concrete footings have been poured, the block and beam floors have been fitted and we are now erecting the timber frames.


Footings complete, awaiting timber frame.
 







Plots 6-9 Timber Frame Nearly Complete.