This week has seen the fitting of the windows and doors to all plots and the commencement of first fix works, by electricians, plumbers and carpenters.
8 New Dwellings Tibberton Gloucestershire
Wednesday, 16 July 2014
Friday, 20 June 2014
Wednesday, 18 June 2014
Wednesday, 4 June 2014
Week 9.
The carpenters have fitted the fascia's and soffits and the roofers have felt and battened plots 6-9.
Wednesday, 21 May 2014
Introduction
The development for Guinness Hermitage began approximately 8 weeks ago, with the clearing of the site and establishment of the site facilities and compound.
Since then we have installed 90% of the underground drainage, all of the concrete footings have been poured, the block and beam floors have been fitted and we are now erecting the timber frames.
Since then we have installed 90% of the underground drainage, all of the concrete footings have been poured, the block and beam floors have been fitted and we are now erecting the timber frames.
Footings complete, awaiting timber frame.
Plots 6-9 Timber Frame Nearly Complete.